Bridge-in-a-Backpack(TM). Task 4 : monitoring and load rating.
-
2015-01-01
-
Details:
-
Creators:
-
Corporate Creators:
-
Subject/TRT Terms:
-
Publication/ Report Number:
-
Resource Type:
-
Geographical Coverage:
-
Corporate Publisher:
-
Abstract:Five bridges were constructed utilizing UMaine’s hybrid composite arch technology as part of the Maine
Department of Transportation’s Composites Initiative. Three were constructed in 2010, one in 2011 and the final
one in 2012. The designs for each of the first four were completed in 2010 and the final design of the Grey’s Brook
Bridge in Ellsworth, Maine (2012 construction) was completed in 2011 using lessons learned from the construction
of the 2010 bridges. Highlights of the construction process, lessons learned, inspection observations, and load testing
are presented in this report for the first four bridges (2010 and 2011 seasons).
-