An Evaluation of the Hyperfix Project for the Reconstruction of I-65/70 in Downtown Indianapolis
-
2004-09-01
-
Details
-
Creators:
-
Corporate Creators:
-
Corporate Contributors:
-
Subject/TRT Terms:
-
Publication/ Report Number:
-
Resource Type:
-
Geographical Coverage:
-
Edition:Draft Final Report
-
Corporate Publisher:
-
Abstract:In 2003 the Indiana Department of Transportation executed an ambitious interstate reconstruction project in Indianapolis, named Hyperfix. This project completely closed the I-65/70 section during reconstruction, on which approximately 250,000 vehicles travel daily. Due to the scope and risk involved, an extensive amount of planning, coordination, and cooperation occurred. The main section was rebuilt during the total closure phase, which lasted 55 days. The total closure approach had never been performed before by INDOT on such a high-volume artery in a downtown metropolitan area. This present study analyzed the project and its impact on the Indianapolis area. The report includes findings on planning and design issues, contractor and INDOT operations, traffic impact, business impact, the park and ride service implemented, and other issues related to total closure.
-
Format:
-
Funding:
-
Collection(s):
-
Main Document Checksum:urn:sha-512:34c3911408cf489ccf7b806948b97b6eb1b66823c9e8673af5432d50b3eac23ce5895c157aa6eceb7f0c62c87579c59b15bbd9deab2b680f67eb06af360049e5
-
Download URL:
-
File Type: