Case Studies Documenting Lessons Learned and Identifying Opportunities for Maintenance of Traffic (MOT) Improvements [Brief]

File Language:
English


Details

  • Creators:
  • Corporate Creators:
  • Corporate Contributors:
  • Subject/TRT Terms:
  • Resource Type:
  • Geographical Coverage:
  • Edition:
    Technical Summary
  • Corporate Publisher:
  • Abstract:
    Over the past 18 months, the team has performed several dozen after-action reviews of interstate work zones and the associated maintenance of traffic (MOT). These after-action reports generally contain the following information: Date, location, visual images, connected vehicle summary graphics, qualitative discussion of activity, and in some cases press releases or media posts. In general, these themes emerged:

    1.MOT plans in some cases do not accurately capture the geometry constraints placed by bridges, guardrail and or barrier wall. It is important that design reviews place careful focus on ensuring lane widths, shoulders, and shoulder treatments fit across the entire cross section of each phase or requests for design exceptions be initiated. In some cases, performing some type of LiDAR survey prior to design may assist MOT designers in effectively capturing more accurate location and dimensions of existing geometrics, particularly edge of pavement, edge of bridge, guardrails, and embankments.

    2.When lane shifts are initiated, the designers should examine the path of the vehicle at both the start and end of the transition. In some cases, the end of the transition occurs quite close to either a guardrail or narrow section of pavement. In some cases, either gentler transitions or additional horizontal clearance should be considered.

    3.There is relatively little dialog between the temporary traffic control contractors and designers on what are the best practices and requirements for implementing a change in MOT.

    4.To sustain this engagement between designers, and MOT contractors, it is recommended that selected projects include MOT review with design engineers, and contractor as part of the close out process to document lessons learned.

    5.Rolling slows downs have a role in MOT, but there appears to be inconsistent use of rolling slowdowns for short term closures. It is recommended that requirements for rolling slowdowns be identified in the MOT plans. If contractors are required to use rolling slowdowns not documented in MOT plans, they should be required to obtain approval from the Indiana Department of Transportation and notify the Traffic Management Center.

    6.Barrier walls are an important tool for MOT. However, their set up can have significant impact on traffic capacity and create queues. Project plans should define days/time periods these are permitted to be installed and/or removed.

  • Format:
  • Funding:
  • Collection(s):
  • Main Document Checksum:
    urn:sha-512:93c195f8a2f91360d7bb63d145872e1b1ac73a12fce925616041822673527ddfa53237c973a7c52b7c1aae3d865d290e9f3a1ff54eb0b149506bbb17b6286c95
  • Download URL:
  • File Type:
    Filetype[PDF - 1.74 MB ]
File Language:
English
ON THIS PAGE

ROSA P serves as an archival repository of USDOT-published products including scientific findings, journal articles, guidelines, recommendations, or other information authored or co-authored by USDOT or funded partners. As a repository, ROSA P retains documents in their original published format to ensure public access to scientific information.