Optimizing Missouri's Statewide Transportation Improvement Program Letting and Construction Schedule
-
2026-03-01
-
Details
-
Creators:
-
Corporate Creators:
-
Corporate Contributors:
-
Subject/TRT Terms:
-
Publication/ Report Number:
-
Resource Type:
-
Geographical Coverage:
-
Edition:Final Report (October 2024-March 2026)
-
Corporate Publisher:
-
Abstract:This study evaluated how Missouri’s annual letting calendar could be structured to improve competition and lower award costs while remaining feasible under existing policies and delivery practices. Historical bid outcomes were used to estimate monthly “performance curves” that related workload share to observed price behavior. A genetic algorithm then assigned projects across roughly eleven monthly lettings to minimize expected awards, subject to practical constraints. Contractor capacity was reflected implicitly in the curves and examined explicitly through a backlog based probabilistic bidding check.
-
Format:
-
Funding:
-
Collection(s):
-
Main Document Checksum:urn:sha-512:52b0194c1799d26b8406e9bf5aa08fb7bdec5ed5c9f54f044cbf279c815771af0455b687f2ab151630a723a0d2ff987f0a10cfebfa4b5a22d17e85fc681642d9
-
Download URL:
-
File Type: