Design of High-Throughput Hump Yards
-
1969-06-01
-
Details:
-
Creators:
-
Corporate Creators:
-
Corporate Contributors:
-
Subject/TRT Terms:
-
Resource Type:
-
Geographical Coverage:
-
Edition:Final Report- Phase 1
-
Corporate Publisher:
-
Abstract:This report covers the work done during a six-month study of design of hump yards to achieve increased throughput. The basic functions of hump yard operation were analyzed and those factors that limit throughput were studied in detail. A modified yard design and freight car control policy was developed that will make possible the design of a hump yard with throughputs ranging from 300 ft to 500 ft of car/min. An evolutionary hump yard design is outlined to permit initial operation at 300 ft of car/min with the capability of increasing this to 400 or 500 ft of car/min by the addition and relocation of the control retarders.
-