Field manual for the operation of advance warning of end of green system (AWEGS).
-
2009-10-01
Details:
-
Alternative Title:Project title: Implementation of Advance Warning of End of Green Systems (AWEGS)
-
Creators:
-
Corporate Creators:
-
Corporate Contributors:
-
Subject/TRT Terms:
-
Publication/ Report Number:
-
Resource Type:
-
Geographical Coverage:
-
Edition:Product; Mar. 2007-Aug. 2008.
-
Corporate Publisher:
-
Abstract:The objective of this implementation project was to implement four AWEGS across Texas at intersections
appropriate for the installation of AWEGS. After a survey across Texas, four sites were chosen in the Atlanta
District, Pharr District, Odessa District, `and San Antonio District. The AWEGS design plans were prepared
for these four sites and submitted to the districts. These design plans were prepared for an intersection with
high-speed approaches having the required dilemma zone detection design. The Atlanta District
implementation was typical of the earlier implementation and used the TS-2 TS-1 conversion panel.
However, the remaining implementations were configured for using enhanced BIUs. AWEGS software was
also modified to account for rail preemption as the site in the Odessa District was being preempted by
between 15 to 25 trains per day. Finally the implementation in the San Antonio District was redesigned to use
radar detection for both dilemma zone and advance detection. AWEGS at the Atlanta, Pharr, San Antonio,
and Odessa Districts have been implemented, and an evaluation of the system showed that AWEGS was
performing satisfactorily at all sites.
-