Lloyd, J. B., & Connor, R. J. (2023). Field Testing and Long-Term Monitoring of Selected High-Mast Lighting Towers (Phase 2) [Data Management Plan]. Wyoming. Department of Transportation. https://rosap.ntl.bts.gov/view/dot/72466
Lloyd, Jason B and Robert J. Connor. Field Testing and Long-Term Monitoring of Selected High-Mast Lighting Towers (Phase 2) [Data Management Plan]. Wyoming. Department of Transportation, 2023. https://rosap.ntl.bts.gov/view/dot/72466.
Lloyd, Jason B, and Robert J. Connor Field Testing and Long-Term Monitoring of Selected High-Mast Lighting Towers (Phase 2) [Data Management Plan]. Wyoming. Department of Transportation, 2023, ROSA P. https://rosap.ntl.bts.gov/view/dot/72466.
Phase 1 field monitoring of four high-mast lighting towers (HMLTs) was previously reported on in March 2020. Due to the rare nature of the large amplitude vibration events, a second phase of monitoring was conducted to continue collecting data and to maximize the potential for recording the rare data. Similar to Phase 1, monitoring, Phase 2 included four HMLT instrumented with sensors to monitor weather and structural response to wind-induced vibrations. The four HMLTs were in different locales within the state of Wyoming, each site being selected specifically due to a history of failed HMLTs at those locations, or nearby. Several HMLTs have failed in recent years, some catastrophically, within Wyoming, from fatigue crack growth at the base plate-to-tube wall welds. Hence, the motivation for the study.
Four high-mast lighting towers (HMLTs) were instrumented with sensors to monitor weather and structural response to wind-induced vibrations. The four
...
Four high-mast lighting towers (HMLTs) were instrumented with sensors to monitor weather and structural response to wind-induced vibrations. The four
...
Lloyd, J. B., & Connor, R. J. (2023). Field Testing and Long-Term Monitoring of Selected High-Mast Lighting Towers (Phase 2) [Data Management Plan]. Wyoming. Department of Transportation. https://rosap.ntl.bts.gov/view/dot/72466
Lloyd, Jason B and Robert J. Connor. Field Testing and Long-Term Monitoring of Selected High-Mast Lighting Towers (Phase 2) [Data Management Plan]. Wyoming. Department of Transportation, 2023. https://rosap.ntl.bts.gov/view/dot/72466.
Lloyd, Jason B, and Robert J. Connor Field Testing and Long-Term Monitoring of Selected High-Mast Lighting Towers (Phase 2) [Data Management Plan]. Wyoming. Department of Transportation, 2023, ROSA P. https://rosap.ntl.bts.gov/view/dot/72466.
ROSA P serves as an archival repository of USDOT-published products including scientific
findings, journal articles, guidelines, recommendations, or other information authored or co-authored by
USDOT or funded partners. As a repository, ROSA P retains documents in their original published format to
ensure public access to scientific information.
Links with this icon indicate that you are leaving a Bureau of Transportation
Statistics (BTS)/National Transportation Library (NTL)
Web-based service.
Thank you for visiting.
You are about to access a non-government link outside of
the U.S. Department of Transportation's National
Transportation Library.
Please note: While links to Web sites outside of DOT are
offered for your convenience, when you exit DOT Web sites,
Federal privacy policy and Section 508 of the Rehabilitation
Act (accessibility requirements) no longer apply. In
addition, DOT does not attest to the accuracy, relevance,
timeliness or completeness of information provided by linked
sites. Linking to a Web site does not constitute an
endorsement by DOT of the sponsors of the site or the
products presented on the site. For more information, please
view DOT's Web site linking policy.
To get back to the page you were previously viewing, click
your Cancel button.