Sims, S. L. (1998). An Analysis of the Use of Linear Scheduling Techniques in the Construction Industry. University of Florida (Gainesville). Department of Civil Engineering. https://rosap.ntl.bts.gov/view/dot/61473
Sims, Steven L.. An Analysis of the Use of Linear Scheduling Techniques in the Construction Industry. University of Florida (Gainesville). Department of Civil Engineering, 1998. https://rosap.ntl.bts.gov/view/dot/61473.
Sims, Steven L. An Analysis of the Use of Linear Scheduling Techniques in the Construction Industry. University of Florida (Gainesville). Department of Civil Engineering, 1998, ROSA P. https://rosap.ntl.bts.gov/view/dot/61473.
A construction scheduling technique is presented which is, in many cases, more advantageous, to both the contractor and the owner, than bar charts typically provided by contractors, particularly for projects that are linear in nature or have repetitive activities scheduled in phases (e.g. roads, piping systems, bridge spans, and high rise buildings). The technique is labeled the linear scheduling method because it is most useful in the construction industry for projects that are linear in nature. The technique maps planned or actual work along the length, or stations, of a project versus time. The basic application of this method is described. Examples of practical application are provided, including a comparative analysis based on an actual Florida Department of Transportation construction project. The technique is compared to the more prevalent bar chart technique utilized in such software applications as Prima Vera Project Planner.
Sims, S. L. (1998). An Analysis of the Use of Linear Scheduling Techniques in the Construction Industry. University of Florida (Gainesville). Department of Civil Engineering. https://rosap.ntl.bts.gov/view/dot/61473
Sims, Steven L.. An Analysis of the Use of Linear Scheduling Techniques in the Construction Industry. University of Florida (Gainesville). Department of Civil Engineering, 1998. https://rosap.ntl.bts.gov/view/dot/61473.
Sims, Steven L. An Analysis of the Use of Linear Scheduling Techniques in the Construction Industry. University of Florida (Gainesville). Department of Civil Engineering, 1998, ROSA P. https://rosap.ntl.bts.gov/view/dot/61473.
ROSA P serves as an archival repository of USDOT-published products including scientific
findings, journal articles, guidelines, recommendations, or other information authored or co-authored by
USDOT or funded partners. As a repository, ROSA P retains documents in their original published format to
ensure public access to scientific information.
Links with this icon indicate that you are leaving a Bureau of Transportation
Statistics (BTS)/National Transportation Library (NTL)
Web-based service.
Thank you for visiting.
You are about to access a non-government link outside of
the U.S. Department of Transportation's National
Transportation Library.
Please note: While links to Web sites outside of DOT are
offered for your convenience, when you exit DOT Web sites,
Federal privacy policy and Section 508 of the Rehabilitation
Act (accessibility requirements) no longer apply. In
addition, DOT does not attest to the accuracy, relevance,
timeliness or completeness of information provided by linked
sites. Linking to a Web site does not constitute an
endorsement by DOT of the sponsors of the site or the
products presented on the site. For more information, please
view DOT's Web site linking policy.
To get back to the page you were previously viewing, click
your Cancel button.