Nebraska: 120th Street and Giles Road Bridge, Sarpy County
-
2000-01-01
Details
-
Corporate Creators:
-
Subject/TRT Terms:
-
Publication/ Report Number:
-
Resource Type:
-
Geographical Coverage:
-
Corporate Publisher:
-
Abstract:The high-performance concrete (HPC) 120th Street and Giles Road bridge in Sarpy County, Nebraska consists of three equal 22.9-m (75-ft) spans and is 25.8 m (84.7 ft) wide. The HPC bridge used seven NU1100 (1100-mm-high) simple-span girders made continuous for live load using negative-moment reinforcement in the deck. The NU girder series is metric. These Bulb-Tee girders were developed in a girder optimization program conducted by the University of Nebraska at Omaha. Girder spacing is 3.8 m (12.4 ft) on center and the deck thickness is 191 mm (7.5 in.). The benefits are apparent as fewer girders were required in the HPC superstructure. A nearby bridge constructed without HPC provides a direct comparison of the durability aspects of HPC.
-
Format:
-
Collection(s):
-
Main Document Checksum:urn:sha-512:2b7a80c8b14ef940d135bd76c0a70e25e9217f8866c11459c06dcd2ae19a379177e53e7a6defdb4c5b6f65b53a44acfbfa1c9f23c3b813758e699d67ef219ef5
-
Download URL:
-
File Type: