Hulsey, J. L., & Delaney, D. K. (1989). Cable Stayed Static Linear Analysis for the Captain William Moore Creek Bridge. Final Report (Report No. FHWA-AK-RD-90-08A ,INE 88.44). Alaska. Dept. of Transportation and Public Facilities. https://rosap.ntl.bts.gov/view/dot/38866
Hulsey, J. Leroy and David K. Delaney. Cable Stayed Static Linear Analysis for the Captain William Moore Creek Bridge. Final Report. Report no. FHWA-AK-RD-90-08A ,INE 88.44. Alaska. Dept. of Transportation and Public Facilities, 1989. https://rosap.ntl.bts.gov/view/dot/38866.
Hulsey, J. Leroy, and David K. Delaney Cable Stayed Static Linear Analysis for the Captain William Moore Creek Bridge. Final Report. Alaska. Dept. of Transportation and Public Facilities, 1989, Report no. FHWA-AK-RD-90-08A ,INE 88.44, ROSA P. https://rosap.ntl.bts.gov/view/dot/38866.
A 300-ft cable-stayed bridge, located on the highway between Skagway, Alaska and Carcross, Canada, is used to carry loaded ore trucks that weigh approximately 160,000 lbs and normal light traffic that consists of campers, buses, and automobiles. The bridge is a two-lane structure with a laminated timber deck supported by transverse floor beams spanning two stiffened ASTM A588 steel box girders. The box girders have 20-, 30-, 123-, and 127-ft span lengths. The bridge was instrumented to evaluate the static live-load performance when subjected to a loaded ore truck. Experimental strains and deflections were recorded and compared with a static elastic two-dimensional finite element model. The 2-D model provided satisfactory results with symmetric loads.
Hulsey, J. L., & Delaney, D. K. (1989). Cable Stayed Static Linear Analysis for the Captain William Moore Creek Bridge. Final Report (Report No. FHWA-AK-RD-90-08A ,INE 88.44). Alaska. Dept. of Transportation and Public Facilities. https://rosap.ntl.bts.gov/view/dot/38866
Hulsey, J. Leroy and David K. Delaney. Cable Stayed Static Linear Analysis for the Captain William Moore Creek Bridge. Final Report. Report no. FHWA-AK-RD-90-08A ,INE 88.44. Alaska. Dept. of Transportation and Public Facilities, 1989. https://rosap.ntl.bts.gov/view/dot/38866.
Hulsey, J. Leroy, and David K. Delaney Cable Stayed Static Linear Analysis for the Captain William Moore Creek Bridge. Final Report. Alaska. Dept. of Transportation and Public Facilities, 1989, Report no. FHWA-AK-RD-90-08A ,INE 88.44, ROSA P. https://rosap.ntl.bts.gov/view/dot/38866.
ROSA P serves as an archival repository of USDOT-published products including scientific
findings, journal articles, guidelines, recommendations, or other information authored or co-authored by
USDOT or funded partners. As a repository, ROSA P retains documents in their original published format to
ensure public access to scientific information.
Links with this icon indicate that you are leaving a Bureau of Transportation
Statistics (BTS)/National Transportation Library (NTL)
Web-based service.
Thank you for visiting.
You are about to access a non-government link outside of
the U.S. Department of Transportation's National
Transportation Library.
Please note: While links to Web sites outside of DOT are
offered for your convenience, when you exit DOT Web sites,
Federal privacy policy and Section 508 of the Rehabilitation
Act (accessibility requirements) no longer apply. In
addition, DOT does not attest to the accuracy, relevance,
timeliness or completeness of information provided by linked
sites. Linking to a Web site does not constitute an
endorsement by DOT of the sponsors of the site or the
products presented on the site. For more information, please
view DOT's Web site linking policy.
To get back to the page you were previously viewing, click
your Cancel button.