Three fundamental issues contribute to the scoping process
;
problems:
;
1. The scoping process is inefficient and inconsistent.
;
2. Staffing for scoping is insufficient.
;
3. The programmed project budgets are locked in based on early,
;
uncertain cost estimates.
;
While numerous actions have been recommended, and some
;
piloted, those with the highest impact will be the actions that
;
address these three fundamental issues, as follows:
;
1. Numerous proposed actions will improve the efficiency and
;
consistency of the scoping process. Scoping peer group
;
meetings can provide a vehicle for driving these improvement
;
actions.
;
2. While the effects of staffing shortages can be accommodated
;
somewhat by making the scoping process more efficient, staffing strategies (such as creating higher level, more esteemed
;
scoping/planning positions) should be pursued.
;
3. Further refinement and implementation of the proposed future
;
state of the programming process will provide a framework to
;
allow later locking in of project budgets.
Boehm, T., & Handy, J. (2016). Pre-contract scoping processes value stream mapping (Report No. FHWA/IN/JTRP-2016/30). Purdue University. Joint Transportation Research Program. https://rosap.ntl.bts.gov/view/dot/32234
Boehm, Ted and Jim Handy. Pre-contract scoping processes value stream mapping. Report no. FHWA/IN/JTRP-2016/30. Purdue University. Joint Transportation Research Program, 2016. https://rosap.ntl.bts.gov/view/dot/32234.
Boehm, Ted, and Jim Handy Pre-contract scoping processes value stream mapping. Purdue University. Joint Transportation Research Program, 2016, Report no. FHWA/IN/JTRP-2016/30, ROSA P. https://rosap.ntl.bts.gov/view/dot/32234.
ROSA P serves as an archival repository of USDOT-published products including scientific
findings, journal articles, guidelines, recommendations, or other information authored or co-authored by
USDOT or funded partners. As a repository, ROSA P retains documents in their original published format to
ensure public access to scientific information.
Links with this icon indicate that you are leaving a Bureau of Transportation
Statistics (BTS)/National Transportation Library (NTL)
Web-based service.
Thank you for visiting.
You are about to access a non-government link outside of
the U.S. Department of Transportation's National
Transportation Library.
Please note: While links to Web sites outside of DOT are
offered for your convenience, when you exit DOT Web sites,
Federal privacy policy and Section 508 of the Rehabilitation
Act (accessibility requirements) no longer apply. In
addition, DOT does not attest to the accuracy, relevance,
timeliness or completeness of information provided by linked
sites. Linking to a Web site does not constitute an
endorsement by DOT of the sponsors of the site or the
products presented on the site. For more information, please
view DOT's Web site linking policy.
To get back to the page you were previously viewing, click
your Cancel button.