Pyeon, J. H., & Lee, E. B. (2012). Systematic Procedures to Determine Incentive/Disincentive Dollar Amounts for Highway Transportation Construction Projects [Research Brief]. Mineta Transportation Institute. https://rosap.ntl.bts.gov/view/dot/24490
Pyeon, Jae-Ho and E. B. Lee. Systematic Procedures to Determine Incentive/Disincentive Dollar Amounts for Highway Transportation Construction Projects [Research Brief]. Mineta Transportation Institute, 2012. https://rosap.ntl.bts.gov/view/dot/24490.
Pyeon, Jae-Ho, and E. B. Lee Systematic Procedures to Determine Incentive/Disincentive Dollar Amounts for Highway Transportation Construction Projects [Research Brief]. Mineta Transportation Institute, 2012, ROSA P. https://rosap.ntl.bts.gov/view/dot/24490.
The Federal Highway Administration (FHWA) has encouraged state transportation agencies (STAs) to implement Incentive/Disincentive (I/D) contracting provisions for early project completion to minimize traffic disruption during highway construction. The FHWA recommended that an I/D amount be calculated based on the estimated road user costs on a project-by-project basis. Although general guidelines to determine the I/D dollar amount for a project have also been published by STAs, there is no systematic tool in use to determine optimum I/D dollar amounts for I/D projects considering road user cost, agency cost, contractor’s acceleration cost, and contractor’s cost savings. Therefore, systematic procedures and models to assist project planners and engineers in determining an appropriate I/D dollar amount are essential to optimizing the use of I/D contracting techniques.
Pyeon, J. H., & Lee, E. B. (2012). Systematic Procedures to Determine Incentive/Disincentive Dollar Amounts for Highway Transportation Construction Projects [Research Brief]. Mineta Transportation Institute. https://rosap.ntl.bts.gov/view/dot/24490
Pyeon, Jae-Ho and E. B. Lee. Systematic Procedures to Determine Incentive/Disincentive Dollar Amounts for Highway Transportation Construction Projects [Research Brief]. Mineta Transportation Institute, 2012. https://rosap.ntl.bts.gov/view/dot/24490.
Pyeon, Jae-Ho, and E. B. Lee Systematic Procedures to Determine Incentive/Disincentive Dollar Amounts for Highway Transportation Construction Projects [Research Brief]. Mineta Transportation Institute, 2012, ROSA P. https://rosap.ntl.bts.gov/view/dot/24490.
ROSA P serves as an archival repository of USDOT-published products including scientific
findings, journal articles, guidelines, recommendations, or other information authored or co-authored by
USDOT or funded partners. As a repository, ROSA P retains documents in their original published format to
ensure public access to scientific information.
Links with this icon indicate that you are leaving a Bureau of Transportation
Statistics (BTS)/National Transportation Library (NTL)
Web-based service.
Thank you for visiting.
You are about to access a non-government link outside of
the U.S. Department of Transportation's National
Transportation Library.
Please note: While links to Web sites outside of DOT are
offered for your convenience, when you exit DOT Web sites,
Federal privacy policy and Section 508 of the Rehabilitation
Act (accessibility requirements) no longer apply. In
addition, DOT does not attest to the accuracy, relevance,
timeliness or completeness of information provided by linked
sites. Linking to a Web site does not constitute an
endorsement by DOT of the sponsors of the site or the
products presented on the site. For more information, please
view DOT's Web site linking policy.
To get back to the page you were previously viewing, click
your Cancel button.