Gurganus, C., Goehl, D., & Estakhri, C. (2022). Success of a 4-Year Pavement Management Plan (Report No. FHWA/TX-23/0-7101-R1). Texas A&M Transportation Institute. https://rosap.ntl.bts.gov/view/dot/65836
Gurganus, Charles, Darlene Goehl, and Cindy Estakhri. Success of a 4-Year Pavement Management Plan. Report no. FHWA/TX-23/0-7101-R1. Texas A&M Transportation Institute, 2022. https://rosap.ntl.bts.gov/view/dot/65836.
Gurganus, Charles, et al. Success of a 4-Year Pavement Management Plan. Texas A&M Transportation Institute, 2022, Report no. FHWA/TX-23/0-7101-R1, ROSA P. https://rosap.ntl.bts.gov/view/dot/65836.
Successful 4-year pavement management plans help provide the traveling public with a safe, comfortable, and reliable roadway network. Each maintenance section plays a role in executing an effective 4-year pavement management plan. To continue to improve the statewide system and get the most value out of fiscally constrained budgets, pavement management plan best practices are needed. Many best practices exist within Texas and are captured as part of this research project. Promoting teamwork and communication at all levels within a district ensures pavement management plans are developed and deployed effectively. Acknowledging that district seal coat projects and seal coat preparations serve as the cornerstone for long-term pavement management success is a key ingredient. For overlay and rehabilitation projects, properly scoring and prioritizing projects helps ensure plan success. Project success is required to improve plan success, and building a preliminary project scope during early project rides and connecting that scope with additional testing needs helps districts transition from plan success to project success to pavement management success.
This project investigated and synthesized best practices for the development and execution of 4-year pavement management plans (PMPs) within the Texas
...
Gurganus, C., Goehl, D., & Estakhri, C. (2022). Success of a 4-Year Pavement Management Plan (Report No. FHWA/TX-23/0-7101-R1). Texas A&M Transportation Institute. https://rosap.ntl.bts.gov/view/dot/65836
Gurganus, Charles, Darlene Goehl, and Cindy Estakhri. Success of a 4-Year Pavement Management Plan. Report no. FHWA/TX-23/0-7101-R1. Texas A&M Transportation Institute, 2022. https://rosap.ntl.bts.gov/view/dot/65836.
Gurganus, Charles, et al. Success of a 4-Year Pavement Management Plan. Texas A&M Transportation Institute, 2022, Report no. FHWA/TX-23/0-7101-R1, ROSA P. https://rosap.ntl.bts.gov/view/dot/65836.
ROSA P serves as an archival repository of USDOT-published products including scientific
findings, journal articles, guidelines, recommendations, or other information authored or co-authored by
USDOT or funded partners. As a repository, ROSA P retains documents in their original published format to
ensure public access to scientific information.
Links with this icon indicate that you are leaving a Bureau of Transportation
Statistics (BTS)/National Transportation Library (NTL)
Web-based service.
Thank you for visiting.
You are about to access a non-government link outside of
the U.S. Department of Transportation's National
Transportation Library.
Please note: While links to Web sites outside of DOT are
offered for your convenience, when you exit DOT Web sites,
Federal privacy policy and Section 508 of the Rehabilitation
Act (accessibility requirements) no longer apply. In
addition, DOT does not attest to the accuracy, relevance,
timeliness or completeness of information provided by linked
sites. Linking to a Web site does not constitute an
endorsement by DOT of the sponsors of the site or the
products presented on the site. For more information, please
view DOT's Web site linking policy.
To get back to the page you were previously viewing, click
your Cancel button.