U.S. DOT Gulf Coast Study, Phase 2, Engineering Case Study 3: Bridge Approach Embankment Exposure to Sea Level Rise
-
2015-01-01
Details
-
Corporate Creators:
-
Contributors:
-
Subject/TRT Terms:
-
Publication/ Report Number:
-
Resource Type:
-
Geographical Coverage:
-
Corporate Publisher:
-
Abstract:This is one of 11 engineering case studies conducted under the Gulf Coast, Phase 2 Project. This case study focused on whether the current riprap embankment protection along the US 90/98 Tensaw-Spanish River Bridge approach is sufficient to protect against increased wave impacts from sea level rise.
-
Format:
-
Collection(s):
-
Main Document Checksum:urn:sha-512:19ab8b851e802b37d82f07b353fdfe9bbaa05e28e2edc210d2c118a56e893f913b523482d880e68f86f8f7203b4e0c414b9d1e12ce3d6caf5c940cff353fdd22
-
Download URL:
-
File Type: