I-85 Interchange Design-Build Project Using Prefabricated Bridge Elements in West Point, GA

File Language:
English


Details

  • Creators:
  • Corporate Creators:
  • Contributors:
  • Corporate Contributors:
  • Subject/TRT Terms:
  • Resource Type:
  • Geographical Coverage:
  • Edition:
    Final Report
  • Corporate Publisher:
  • Abstract:
    As part of a national initiative sponsored by the Federal Highway Administration under the Highways for LIFE program, the Georgia Department of Transportation (GDOT) was awarded a $1 million grant to demonstrate the use of proven, innovative technologies to deliver an $81 million project in less time than conventional construction. In addition, this was a 100 percent Federally funded project. This report documents the design-build project in Troup County to construct a new Interstate 85 interchange, 10 miles (16 kilometers) of four-lane frontage and access roadway, another bridge, and all other items associated with this large economic development project. The interchange includes prefabricated bridge substructure elements, used for the first time in the State. This report discusses the use of the design-build (D-B) contracting method, a first for Georgia, implemented under newly passed State legislation. The project also includes other firsts for Georgia, including requiring the D-B contractor to propose state-of-the-art methods to achieve performance expectations, the use of prefabricated elements to construct the bridge substructure and real-time traffic operations support through speed band monitoring on I-85. GDOT also set traffic incident response time goals for this project. Under conventional construction, the impact of this project on the traveling public was estimated at 30 months, but with the use of the D-B contracting technique and prefabricated bridge elements, the impact was reduced to only 16.5 months. Using D-B and other innovative techniques to accelerate the delivery schedule had a significant influence on the net construction cost. A comprehensive economic analysis including construction costs and user costs shows that the project saved about $1.98 million or about 45 percent over traditional contracting and construction methods. Because of the success of this project, GDOT is more comfortable with using the D-B method and prefabricated bridge elements on future largescale projects.
  • Format:
  • Collection(s):
  • Main Document Checksum:
    urn:sha-512:908830e36c66c0a9cb8a22a50c7e28c63434675e9c81c75a0a45bb3c50b3f7d24a5a3782343d09dfcfacf640579939230a1c7079d30283c9e1890e9256cc2f7b
  • Download URL:
  • File Type:
    Filetype[PDF - 2.73 MB ]
File Language:
English
ON THIS PAGE

ROSA P serves as an archival repository of USDOT-published products including scientific findings, journal articles, guidelines, recommendations, or other information authored or co-authored by USDOT or funded partners. As a repository, ROSA P retains documents in their original published format to ensure public access to scientific information.