Scully, T. C. (2019). Audubon Parkway Slab Lifting at MP 22.75 — Bridge Approach and Departure Settlement (Report No. KTC-19-17/KHIT106-1F). University of Kentucky Transportation Center. https://doi.org/10.13023/ktc.rr.2019.17
Scully, Tim C.. Audubon Parkway Slab Lifting at MP 22.75 — Bridge Approach and Departure Settlement. Report no. KTC-19-17/KHIT106-1F. University of Kentucky Transportation Center, 2019. https://doi.org/10.13023/ktc.rr.2019.17.
Scully, Tim C. Audubon Parkway Slab Lifting at MP 22.75 — Bridge Approach and Departure Settlement. University of Kentucky Transportation Center, 2019, Report no. KTC-19-17/KHIT106-1F, ROSA P. https://doi.org/10.13023/ktc.rr.2019.17.
The approach/departure Portland Cement Concrete (PCC) panels on the eastbound and westbound side of Audubon Parkway at MP 22.75 over route KY 2120 began to exhibit settlement and cracking in a few locations, which created an uncomfortable ride for motorists. To address this problem, the Kentucky Transportation Cabinet (KYTC) contracted with MasterDry to repair the PCC panel settlement. MasterDry claims that its two-part polyurethane material expands into a rigid foam that fills voids, stabilizes slabs, and lifts concrete. The polyurethane material is injected through 5/8-inch holes drilled in the PCC panel. Once injected, a chemical reaction converts the liquid urethane components to a strong, rapidly-setting foam material. With a compressive strength of 100 pounds per square inch, polyurethane offers the necessary strength to support heavy loads. At the request of KYTC the Kentucky Transportation Center (KTC) has monitored and evaluated the performance of MasterDry’s polyurethane foam treatment. To determine effectiveness of the lifting agent, elevation data were collected. A falling weight deflectometer (FWD) was used to assess the condition of in situ base materials and load transfer efficiency (LTE).
Scully, T. C. (2019). Audubon Parkway Slab Lifting at MP 22.75 — Bridge Approach and Departure Settlement (Report No. KTC-19-17/KHIT106-1F). University of Kentucky Transportation Center. https://doi.org/10.13023/ktc.rr.2019.17
Scully, Tim C.. Audubon Parkway Slab Lifting at MP 22.75 — Bridge Approach and Departure Settlement. Report no. KTC-19-17/KHIT106-1F. University of Kentucky Transportation Center, 2019. https://doi.org/10.13023/ktc.rr.2019.17.
Scully, Tim C. Audubon Parkway Slab Lifting at MP 22.75 — Bridge Approach and Departure Settlement. University of Kentucky Transportation Center, 2019, Report no. KTC-19-17/KHIT106-1F, ROSA P. https://doi.org/10.13023/ktc.rr.2019.17.
ROSA P serves as an archival repository of USDOT-published products including scientific
findings, journal articles, guidelines, recommendations, or other information authored or co-authored by
USDOT or funded partners. As a repository, ROSA P retains documents in their original published format to
ensure public access to scientific information.
Links with this icon indicate that you are leaving a Bureau of Transportation
Statistics (BTS)/National Transportation Library (NTL)
Web-based service.
Thank you for visiting.
You are about to access a non-government link outside of
the U.S. Department of Transportation's National
Transportation Library.
Please note: While links to Web sites outside of DOT are
offered for your convenience, when you exit DOT Web sites,
Federal privacy policy and Section 508 of the Rehabilitation
Act (accessibility requirements) no longer apply. In
addition, DOT does not attest to the accuracy, relevance,
timeliness or completeness of information provided by linked
sites. Linking to a Web site does not constitute an
endorsement by DOT of the sponsors of the site or the
products presented on the site. For more information, please
view DOT's Web site linking policy.
To get back to the page you were previously viewing, click
your Cancel button.