QuickZone: Case Study Snapshot #3: Responding to Public Concern about Delays during Bridge Repairs
Advanced Search
Select up to three search categories and corresponding keywords using the fields to the right. Refer to the Help section for more detailed instructions.

Search our Collections & Repository

For very narrow results

When looking for a specific result

Best used for discovery & interchangable words

Recommended to be used in conjunction with other fields

Dates

to

Document Data
Library
People
Clear All
Clear All

For additional assistance using the Custom Query please check out our Help Page

i

QuickZone: Case Study Snapshot #3: Responding to Public Concern about Delays during Bridge Repairs

Filetype[PDF-804.99 KB]


English

Details:

  • Corporate Creators:
  • Contributors:
  • Corporate Contributors:
  • Subject/TRT Terms:
  • Publication/ Report Number:
  • Resource Type:
  • Geographical Coverage:
  • Corporate Publisher:
  • Abstract:
    In the spring of 2001, a major structural rehabilitation project started on the Little Bras d’Or bridge in Nova Scotia, Canada. Built in 1959, the bridge consists of 1.2 meter by 30.4 meter (4 feet by 100 feet) steel girder spans and carries a two-lane, twoway highway. It was necessary to close one lane to perform repairs. Traffic flow was controlled by signals, and later, during peak traffic flow hours, by flaggers. As the project progressed into late spring, traffic volumes increased and motorists began to experience significant delays. Local residents, businesses, politicians, and emergency services were very vocal about the delays. Political pressure forced rescheduling the work for November of that year. In anticipation of the November bridge work, the Province’s transportation engineer started looking for tools to help predict the impact of the proposed closure to make objective decisions on when work could take place. QuickZone was used to analyze various staging scenarios. First, a baseline model was validated for queues and delays observed during the spring 2001 roadwork. QuickZone demonstrated that the planned move to November using the same traffic control would still result in unacceptable delays. Due to the QuickZone analysis and political issues, project completion was further delayed. Basic repairs were made to keep the bridge safely open until a better traffic control solution could be identified. In 2004, the initial analysis performed at this site was updated for a milling and repaving project on the same section of the highway. Estimates of capacity loss were updated based upon observations made at other sites. QuickZone was used to support the decision to do the work at night and also to define allowable nighttime work hours. It is anticipated that the structural repairs started in 2001 will resume and be completed in 2005 using an alternative traffic control plan.
  • Format:
  • Alternate URL:
  • Collection(s):
  • Main Document Checksum:
  • Download URL:
  • File Type:

Supporting Files

  • No Additional Files
More +

You May Also Like

Checkout today's featured content at rosap.ntl.bts.gov