Risk analysis of ODOT’s HMA percent within limits (PWL) specification.
-
2007-08-01
Details:
-
Creators:
-
Corporate Creators:
-
Corporate Contributors:
-
Subject/TRT Terms:
-
Publication/ Report Number:
-
Resource Type:
-
Geographical Coverage:
-
Edition:Final report.
-
Corporate Publisher:
-
Abstract:The Oklahoma Department of Transportation (ODOT) is considering switching its method of payment
for hot mix asphalt (HMA) construction from their current procedure to a Percent Within Limits (PWL)
specification. Quality characteristics are percent asphalt content (%AC), percent laboratory compacted air
voids (%AV) and percent roadway density (%RD). As the PWL methodology is new to both ODOT and
its contractors, there is concern that differences between the methodologies could result in significant
differences in the payments awarded for contracted HMA work.
A risk based simulation approach, using Monte Carlo simulation, was structured to evaluate the
probabilities that PWL’s generated randomly from a representative data base structured from ODOT
paving projects would be within “acceptable” limits. In this way ODOT would be able to assess the
expected performance and pay structure resulting from adoption of the PWL methodology against a set of
previously collected data.
The data set provided by ODOT showed that contractors are, on average, hitting the target value for
asphalt content but running 0.37 and 0.9 percent below the target value for %AV and %RD, respectively.
Comparisons of the ODOT generated data to data sets found in the literature indicate that the ODOT data
set contains a high measure of control, while the simulation efforts showed that average performance for
both %AC and %RD would earn bonuses but less than full pay for %AV, and less than full pay for the
lot.
The draft PWL specification as currently written appears to not fairly reward a contractor for a high
level of quality control. Recommendations for adjustments in the target limits and specification limits
were made. It is recommended that ODOT proceed slowly with the implementation of PWL
specifications until a sufficiently large data base can be obtained and the analysis repeated to verify any
changes to specification and target limits.
-