Analysis of change orders in geotechnical engineering work at INDOT.
-
2011-01-01
Details
-
Alternative Title:Joint Transportation Research Program : Civil Engineering
-
Creators:
-
Corporate Creators:
-
Corporate Contributors:
-
Subject/TRT Terms:
-
Publication/ Report Number:
-
Resource Type:
-
Geographical Coverage:
-
Corporate Publisher:
-
Abstract:Change orders represent a cost to the State and to tax payers that is real and often extremely large because contractors tend to charge very large ; amounts to any additional work that deviates from the work that was originally planned. Therefore, efforts must be made to reduce significantly the occurrence ; of change orders in order to provide significant cost savings to the state of Indiana and save taxpayer dollars. The proposed research, in this context, developed ; a set of guidelines that will allow the geotechnical office of the Indiana Department of Transportation (INDOT) to minimize the probabilities of having change ; orders in those projects where they are truly preventable. These guidelines include not only recommendations on how to manage the problem of change orders ; associated with the geotechnical construction projects when they are unavoidable but also general recommendations wherever possible for adequate site ; investigation, design procedures, and quality assurance and quality control (QA/QC) processes that could help minimize change orders. ; Based on the analysis conducted on the data collected from 300 INDOT contracts, it was found that the average geotechnical change order amount per ; district per year was 1.34 percent of the total estimated construction cost per district per year. The average geotechnical change order amount per district per ; year was 10.25 percent of the average amount of total change orders per district per year. The average net overrun due to geotechnical change orders was ; $707,000 per district per year. About 28 percent (84 contracts) of the contracts that were considered in this study experienced geotechnical change orders. In ; total, 158 geotechnical change orders were recorded in all the contracts. About 41 % of the total road contracts (155 contracts) experienced geotechnical ; change orders. About 37% of the total bridge contracts (44 contracts) experienced geotechnical change orders. The other contract types of this study’s dataset ; were insignificant as far as geotechnical change orders were concerned. Reason code 206 – Constructability: Soils-Related – was assigned to 101 geotechnical ; change orders. Reason code 405 – Changed Field Conditions: Soils-Related – was assigned to 46 geotechnical change orders. Reason code 108 – Errors and ; Omissions: Soils-Related – was assigned to the 11 remaining geotechnical change orders. INDOT personnel who were interviewed acknowledged the fact that ; the variability of soil is so great that it would be literally impossible to eliminate geotechnical change orders. However, they did recognize the need to address ; the following issues that lead to geotechnical change orders (i) Failure to identify areas of poor subgrade soil (ii) Mismatch in piling quantities (iii) Omissions ; and constructability issues associated with erosion control work.
-
Format:
-
Funding:
-
Download URL:
-
File Type:
-
Collection(s):
-
Main Document Checksum:urn:sha-512:660b5ab239606d1ea84d435f2a5597032510d3de26df8bb5f488bb902099f8dc229c97d0d35529c611c194a82d04fb0d3e17b09de273e9d30b7be6873b962d1b