Assessing performance characteristics of sediment basins constructed in Franklin County.
-
2012-08-01
Details
-
Creators:
-
Corporate Creators:
-
Corporate Contributors:
-
Subject/TRT Terms:
-
Publication/ Report Number:
-
Resource Type:
-
Geographical Coverage:
-
Corporate Publisher:
-
NTL Classification:NTL-ENERGY AND ENVIRONMENT-ENERGY AND ENVIRONMENT ; NTL-HIGHWAY/ROAD TRANSPORTATION-Construction and Maintenance ; NTL-HIGHWAY/ROAD TRANSPORTATION-Design ; NTL-HIGHWAY/ROAD TRANSPORTATION-Soils and Geology ; NTL-PLANNING AND POLICY-Surveys
-
Abstract:The objective of the research project was to monitor the performance of newly designed ; sediment basins that were constructed on the ALDOT 502 project in Franklin County. The ; project included four tasks: (1) assess performance characteristics of sediment basins on the 502 ; project, (2) collect cost data and perform a literature review, (3) perform a survey of the current ; state-of-the-practice, and (4) prepare project reports. All tasks proposed have been completed. ; Through completing the study, the following conclusions have been developed: ; A field-scale data collection plan to monitor and evaluate sediment basin performance was ; developed and implemented using ISCO 6712 portable automatic stormwater samplers, ; flow modules, a rain gauge, and weirs. ; Sediment basin 4 on the 502 project did effectively remove sediments at the early stage of ; the construction when the basin’s influent most likely contained relative large percent of ; large-size sediment particles. For example, sediment basin 4 removed 97.9% and 83.7% of ; sediments generated by rainfall events on 11/16/2011 and 12/5/2011. ; A floating skimmer allowed for effluent to be discharged uniformly and slowly, providing ; longer detention time for sediments to settle in the basin. Data analyses on decay ; (reduction) coefficients for total suspended solids (TSS) and turbidity allowed us to ; quantify the sediment-settling rate of soils on the 502 project in Franklin County, AL. ; Appropriate PAM (or floc log) added into inflow is crucial to aid sediment settling and ; reduce turbidity of effluent. For example, the performance of the basin 4 was superior for ; the rainfall event on 11/16/2011 when correct PAM was used in the inflow channel than the ; performance for the rainfall event on 12/5/2011 when wrong PAM was used. ; Rainfall events with subsequent high rainfall intensity impulses generated high turbidity ; inflows from the construction site and suddenly increased in-basin turbidity that could be ; several times higher than turbidity of water already in the basin. ; Resuspension of settled sediments significantly increased in-basin sediment concentration ; and turbidity when the basin has experienced a number of rainfall events with large amount ; of settled sediments inside basin. ; An under-designed sediment basin (from a volumetric standpoint) more frequently allowed ; highly turbid sediment-laden runoff to directly flow over the emergency spillway to ; downstream receiving water body. ; Based upon the results of the data collected and observed site conditions throughout the research ; period, the following recommendations are provided to ALDOT to improve sediment basin ; design and installation to maximize performance efficiency and cost effectiveness: ; Use at least 3,600 cubic feet per acre draining to the basin from the contributing area to size ; the sediment basin. ; Increase the number of PAM floc logs placed at the bottom of inflow channel to properly ; dose for the average flow rate of 2-yr 24-hr runoff. The number of floc logs should be ; based on the manufacturer recommended dosage and the expected inflow rate of ; stormwater runoff. ; Consider increasing the number of floc logs placed on the sides of inflow channel to dose ; for the average flow rate of 10-yr 24-hr runoff. These storms will have higher water ; depths, resulting in a greater amount of inflow, therefore requiring a higher dosage of ; PAM. ; The height of the baffles, once installed, should match the full depth of the sediment basin ; and not be installed below the minimum elevation of the emergency spillway. ; Include a sediment storage volume (e.g., 500 ft3/acre disturbed) into the design ; specifications of sediment basins and a requirement to remove the sediment when it reaches ; one third of the height of the sediment storage volume.
-
Format:
-
Download URL:
-
File Type:
-
Collection(s):
-
Main Document Checksum:urn:sha-512:64f798dd9fcf7768e07e5beb1b704d66172e4c315a591bb3089fcb6b24cdf6e0c469399e0775c46bfff96bb9d49dd583056acc58d14c5495a00cf76811f6967f